Rochester – Unit D

Project overview

Strood

Kent

10 weeks

Completion date

28,000 sq ft

Project Size

This was a 10 week industrial refurb project which included roof repairwork (including adding skylights), external cladding repairs and spraying, new roller doors and window repairs. Internally, the unit was stripped out, underwent M&E upgrades, warehouse floor grinding and painting, office and WC upgrades with new ceilings, lighting, power and floor finishes. We have now handed over – on time, and on budget – to a very happy client!

The final 2 photos shows the unit pre-refurb.

Not what you are looking for?

Check out our Design & Build case studies.

Check out our Industrial case studies.